Arjan (Al Barsha South Third) · by Samana Developers · Running late





Homes in this building
What buyers actually paid
7 off-plan sales registered with the Dubai Land Department, June to October 2026.
What's in the building
Payment plan
PDC: 20% booking, 1%/month x30, 10% 6th month, 5% 12th, 5% 18th, 0.5%/month x60. Non-PDC: 25% down, same, 0.5%/month x50
Construction
71% built at the last Dubai Land Department inspection (22 Sept 2026).
Expected handover: Q2 2027. Completion date registered with the Dubai Land Department: 30 Apr 2026.
About this data: The developer's published details and the Dubai Land Department registry agree.