Liwan (DLD: Wadi Al Safa 2) · by ALMA Developments · Running late





What stands out
- fully furnished and fitted apartments
- Al Meera joinery, Kohler fittings
- extra storage
- smart home
Homes in this building
What buyers actually paid
3 off-plan sales registered with the Dubai Land Department, June to October 2026.
What's in the building
Construction
50% built at the last Dubai Land Department inspection (12 Aug 2026).
Was due: Q3 2026 (official; now overdue). Completion date registered with the Dubai Land Department: 15 May 2026.
About this data: The developer's published details and the Dubai Land Department registry agree.